The following information was received from BC Hydro on November 3, 2026
BC Hydro: October update on the Victoria to Esquimalt Cable Replacement
A brief update on the project work and schedule.
Esquimalt Substation area:
- The new bike trail connecting Hereward Road to the E&N Trail was successfully opened in early October.
Banfield Park:
- Our marine works contractor completed the foreshore and riparian work areas on November 2 and demobilized from the site.
- Banfield Park Trail reopening: the lower trail along the water will open before November 20. Detour signs around the area will be removed.
- Our cable crews moved into Banfield Park and Viaduct Park at the end of October to inspect and prepare the cable conduits, and to bring in the large reels via trucks, to pull in the new cables between the two parks and under the Gorge Waterway.
- Three cable reels will be placed in the park this week.
- Cable pulling may take place in mid-November followed by cable splicing within the concrete vaults.
- Banfield Park restoration work is planned to begin in December. Gravels will be removed and the site prepared for a landscape contractor to begin full park restoration of the work area in early January.
Viaduct Park:
- Work continues and the goal for our marine works contractor is to complete the foreshore and riparian area by November 15 and demobilize from the site.
- Our cable crews moved into the park in late October, and as they did in Banfield Park, to prepare to pull in the new cables between the two parks and under the Gorge Waterway.
- Viaduct Park restoration work is planned to begin in December. This includes civil work and prepare the area for a landscape contractor to have the plantings in place by spring 2027.
- The ongoing Galloping Goose Regional Trail (GGRT) closure and detour is in place to spring 2027. The closure is coordinated with BC Hydro, City of Victoria and Capital Regional District and the various capital improvement projects.
- The improved bike path that connects the GGRT to Gorge Road East, thru Viaduct Park, is planned to open by the end of February 2027.
- The improved bike path, when open, will then become part of the GGRT detour – bike traffic will then no longer be detoured onto Waterfront Cresent and the vehicle right turn from Jutland Road southbound onto Waterfront Cresent, at the Jutland Road roundabout, will be reopened.
Gorge Waterway:
- The marine barge work for the cable trench backfilling was completed on September 30, and the barges demobilized from the Gorge Waterway.
- The four temporary piles, used to anchor the barges in place at low tide, remain.
- Saltmarsh (fish habitat off-setting work) construction in Banfield Park: a marine contractor may mobilize with barges and equipment at low tide, to get under the Selkirk Trestle, as early as mid-November. They will anchor to the four temporary piles in the Gorge Waterway on the west side of the trestle.
- Saltmarsh construction may begin as early as mid-November and take place during the winter fisheries work window.
- The work to build the saltmarsh will be done at high tide. The good news is the high tides in the winter are predominantly during the day.
- The November project update will provide more information on this work.
- Saltmarsh construction may begin as early as mid-November and take place during the winter fisheries work window.
Thank you for your ongoing patience. Please let me know if you have any questions. I plan to provide another brief update around the end of November.